Water Engineering Projects and Road Diversions

Sharnden Borehole, Coggins Mill, Mayfield

Work to install 1,450 metres of new raw water main on private land starts on 23 July 2018 with a completion date of 16 January 2019. This water main, connecting the new borehole with Coggins Mill Water Treatment Works, will be laid across Pennybridge Lane which will be closed to through traffic between 10 and 24 September 2018.

Coggins Mill Lane, Mayfield

This will involve a road closure to install 856 metres of new water pipe. This new water main will replace the existing pipe, and help reduce bursts in the area. Work will start on 24 September 2018 for approximately two months with Coggins Mill Lane closed to through traffic.

For more information and the diversion routes please access this link.