MCC Update – June 2024

As the Pre-construction Services Agreement (PCSA) was signed by Wealden District Council (WDC) and the build contractor back in March, the contractor has now appointed a team of professionals, thereby creating a design team including, in particular, the architects.

Following design meetings with the contractor and architect, internal and external elevation drawings along with a site plan have been produced. These will be shared with the Parish as soon as a venue and date can be agreed. Details will also be shared on the village Facebook page and the Parish website. Feedback forms will be made available in order to quantify the public’s views. 

The architect is now working upon the detail behind the basic designs with a view to developing a planning application submission which is planned for July/August 2024.

Assuming planning approval is obtained on schedule, the build contract is expected to be awarded by end December 2024, with completion remaining on schedule for December 2025. 

In addition, both the Legal Heads of Terms for a Development Agreement and the Head Lease are being finalised.

Further information can be found on the village Facebook site and the Mayfield and Five Ashes Parish Council website www.mayfieldfiveashes.org.uk, as it becomes available.